7.2018

Underground parking nearing completion

IMG_6070.jpg

10.2017

Shoring installation is underway to allow for excavation of underground parking garage.


6.2017                 

Overhead power and cable lines throughout the site will be converted to installed underground lines during the month of June.  Water and gas lines have been installed underground to service the new project and connected to Pacific Coast Highway.  Energization of underground lines by SDG&E scheduled to occur on July 8th, 2017.  Amber Lantern closure anticipated on July 10th 2017 to allow for construction of underground parking garage to continue.


1.2017

Utility Work Underway

The developer of Prado West, Raintree Partners, will be upgrading utilities in the downtown area in connection with the development of the project.   The majority of existing overhead power and data lines between the Street of Amber Lantern and the Street of Violet Lantern will be buried underground and out of sight.  This work started in September and is expected to be completed in late spring of 2017.